Chengdu Tram Line 2 is a tram line in Chengdu, China. The line has a total length of 39.3 kilometres (24.4 mi) and 35 stations (and will have 47 in the long term). It has a 'Y' layout and runs from the Chengdu West railway station to Pixian West railway station and Hongguang. The line was officially started in December 2015, and the 13.7 km (8.5 mi) demonstration section of the line was opened on 26 December 2018, and the remaining sections were opened on 27 December 2019.

History

In 2014, Chengdu disclosed the concept of building a modern tram system in the first and second round of rail transit planning. The construction concept of Chengdu Modern Tram System was disclosed in 2014. In September 2015, Chengdu Development and Reform Commission formally issued an agreement to Chengdu IT Avenue Modern Tram with the document "Chengfa Reform Government Approval [2015] No. 216". Route 2 line approval, the same month, the Chengdu Municipal government announced the "urban rail transit network construction to speed up the implementation of the program."

The line started the preliminary construction in December 2015. On 15 April 2016, the proposed naming of the 47 stations on the Chengdu route 2 entered the publicity stage and was approved by the Chengdu Municipal Government in July of the same year. In September 2016, the entire line started construction and the line demonstration site Baiye Road Station was completed in December. In June 2017, Chengdu CRRC Long Passenger Rail Vehicle Company announced the low-floor tram vehicles used on the line. On 25 September of the same year, the first section of the line achieved long-track rail connection, and it was announced that it would open in the first half of 2018.

On 25 January 2018, the first section of the line was energized by the contact network; on August 10, the line completed the "hot slip" test; on September 6, the line was handed over to the operating unit; on September 10, the line started the EMU commissioning work; At the beginning of December, the installation of traffic safety signs for the first opening section was completed. On 26 December 2018, the first section opened for trial operation. On 26 December 2019, the non-initial segment opened.

Timeline

  • 2014 - Construction of a tram network was decided.
  • 2016 - Officially construction was started.
  • 2018 - Commercial service was opened in 26 December.
  • 2019 - Pixian West Railway Station - Chenguang, Hexin Road - Chengdu West Railway Station and branch route opened in 27 December.

Tram route

Station No.Service routesStation nameTransferDistance kmDistrict
MainBranchEnglishChineseMainBranch
92 33Chengdu West Railway Station成都西站Humen railway station CMW 4 9-0-Qingyang
92 32Liangong联工1.1881.188
92 31Qingchun清淳0.8482.036Jinniu
92 30Lianghe Road两河路0.5472.583
92 29Tulong Road土龙路1.0143.597
92 28Xinye Road新业路1.5465.143-0Pidu (W. Hi-Tech Zone)
92 27Jincheng College, Sichuan University锦城学院1.6546.797-
92 26Xinda Road新达路--
92 25University of Electronic Science and Technology of China电子科大1.6048.601
92 24Tianrun Road天润路1.45510.056
92 23Hexin Road合信路0.50810.564
92 22Hezuo Road合作路0.42710.991
92 21Tianxin Road天欣路0.66811.658
92 20Anbu安埠0.94912.607
92 19Tianying Road天映路1.37013.977
92 18Tianyuan Road天源路1.13615.113
92 17Shuxin Avenue蜀新大道--
92 164th Kangqiang Road康强四路--
92 152nd Antai Road安泰二路--
92 145th Antai Road安泰五路--
92 13Defu Avenue德富大道4.80919.923Pidu
92 12Hongqi Avenue红旗大道0.76020.683
92 11Hongzhan East Road红展东路0.39821.081
92 10Dayu East Road大禹东路1.04022.121
92 09Huashi花石0.78822.909
92 08Chenguang晨光1.12624.035
92 07Hegong Road何公路0.82924.864
92 06Wangcong Middle Road望丛中路0.29925.163
92 05Wangcong Temple望丛祠60.46325.626
92 04Hexing Street和兴街0.63226.258
92 03Liyuan Road梨园路0.47426.732
92 02Boluotan菠萝滩0.61727.349
92 01Pixian West Railway Station郫县西站Humen railway station PCW0.46927.818
92 Y1Baiye Road百叶路-1.1151.115Pidu (W. Hi-Tech Zone)
92 Y2Chenfeng晨风1.2292.344
92 Y3Tianhe Road天河路20.6723.016Pidu
92 Y4Xi'an Road犀安路0.6733.689
92 Y5Longyin龙吟0.6754.364
92 Y6Xipu Campus, Southwest Jiaotong University交大犀浦校区6 (via Xingye North Street)0.8335.197
92 Y7Xifang Road犀方路0.9116.108
92 Y8Guoning国宁1.0097.117
92 Y9Datian大田1.1378.254
92 Y10Xihua University西华大学0.6138.867
92 Y11Shuanglin Village双林村0.7619.628
92 Y12Jintu金土0.58910.217
92 Y13Chengdu Technicians College技师学院0.90311.120
92 Y14Renhe仁和0.69811.818

Practical Info

  • Total length - 39.3 km (24.4 mi).
  • Opened - 26 Dec. 2018 (initial); 27 Dec. 2019 (full)
  • Number of Stops - 35
  • Number of routes - 2
  • Gauge - Standard Gauge

The main line of Chengdu Tram Line T2 runs from 07:00-20:40 (to Chengdu West railway station) / 07:00-21:00 (to Pixian West railway station), and the branch line runs from 07:00-20:50 (to Xinye Road)/07:00-21:30 (toward Chenguang), the departure interval is about 10 minutes, and the whole journey takes about 40 minutes.

Fleet

Tram at Chengdu West railway station
interior view of a tram

The Chengdu Tram Line 2 train has three colors of blue-green, light blue and bright yellow. It adopts the Alstom Citadis 302 technology platform 100% low-floor 5-module steel-wheeled tram, 32.6 m (106 ft 11 in) long and 2.65 m (8 ft 8 in) wide, manufactured in Chengdu's CRRC Changchun Railway Vehicles plant. The tram has 64 seats, a capacity of 300 people, and a maximum passenger capacity of 380 people. The average speed of the tram is 23 km/h (14 mph), the maximum speed is 70 km/h (43 mph), the maximum gradient is 60‰, and the minimum turning radius is 20 m (65 ft 7 in), vehicles uses a combination of super capacitor and ordinary catenary power supply to ensure the power when passing through some intersections. The car is equipped with barrier-free facilities and a button to open the door.

Theme tram

When the Chengdu route 2 was fully opened in 2019, a theme tram with the theme of "National Security Archives" went online simultaneously. The painting of the tram is based on the theme of spring, summer, autumn and winter, and nine nationally protected animals are interspersed in the form of illustrations, and corresponding science content is set in the car, calling on citizens to pay attention to and participate in the protection of endangered wild animals.

Depots & termini

Termini are Chengdu West railway station, Pixian West railway station & Renhe.

Alignment and Interchanges

Chengdu Tram Line 2 has a total length of 39.3 km (24.4 mi), of which the elevated section is 1.8 km (1.1 mi) and the ground section is 37.5 km (23.3 mi). Chengdu Tram Line 2 leads from Chengdu West Railway Station, heading northwest to Xinye Road Station, and then along two lines to Pixian West railway station and Renhe. In addition, in 2018, the newly planned Honggao branch line of Chengdu Line 2 leads from Hezuo Road Station to Jintu Station, connecting the Xipi section and the Xinhong section, making the whole line a ring.

Chengdu tram platform

The platform of Chengdu Tram Line 2 is open, and passengers must purchase tickets or swipe cards on the train. The platforms of the first section are all side platforms, and are equipped with half-height screen doors (not in use), seats and train information display screens. The platforms on both sides are not symmetrical and do not communicate directly. For the sake of cost saving and easy maintenance, the subsequent stations did not install half-height screen doors, and replaced the tempered glass railings with wire mesh materials.

Tickets

The fare of the line is two yuan for the whole journey, which is paid by cash or Tianfutong, and supports Tianfutong, Cloud QuickPass or the application of two-dimensional code scanning in Chengdu Metro.

See also